SYS-DDQ611-03 Pre-switch check of Metering Point Characteristics, specify post code and meter number
| Test ID | SYS-DDQ611-03 |
| BRS's | BRS-NO-611 |
| Roles | DDQ |
| Preconditions | Metering point should have metering point status E22 (active) in Elhub Only post code and meter number should be filled out |
| Postconditions | |
Optional/Mandatory | Mandatory |
| Test steps | Expected Result |
1. Send BRS-NO-611
| Request is successfully sent |
2. Receive ResponseUpFrontMeteringPointCharacteristics to DDQ
| ResponseUpFrontMeteringPointCharacteristics s received to DDQ |