Test IDSYS-DDQ305-01
BRS's

BRS-NO-103

BRS-NO-305

Roles

DDQ

Preconditions

Metering point should have metering point status E22 (active) in Elhub

Postconditions

Master data has been updated on the metering point

Optional/Mandatory

Mandatory
Test stepsExpected Result

1. Send BRS-NO-103

  • Message: RequestToElhub
  • Document type: 21
Request is successfully sent

2. Receive ConfirmStartOfSupply to DDQ (optional)

  • Document type: 294
ConfirmStartOfSupply is received to DDQ

3. Receive NotifyStartOfSupply to DDQ

  • Document type: 414
NotifyStartOfSupply is received to DDQ
4. Send an email to post@elhub.no and ask for manual master data update on the metering pointMaster data has successfully been updated on the metering point

5. Receive NotifyMeteringPointCharacteristics to DDQ

  • Document type: E58
NotifyMeteringPointCharacteristics is received to DDQ