Test IDSYS-DDQ302-01
BRS's

BRS-NO-103

BRS-NO-302

Roles

DDM

DDQ

Preconditions

Metering point should have metering point status E22 (active) in Elhub

Postconditions

The information on the metering point have been updated

Optional/Mandatory

Mandatory
Test stepsExpected Result

1. Send BRS-NO-103 to Elhub

  • Message: RequestStartOfSupply
  • Document type: 392
Request is successfully sent

2. Receive ConfirmStartOfSupply to DDQ (optional)

  • Document type: 294
ConfirmStartOfSupply is received to DDQ

3. Receive NotifyStartOfSupply to DDQ

  • Document type: 414
NotifyStartOfSupply is received to DDQ

4. DDM sends BRS-NO-302 to Elhub

  • The Ediel portal is operating as Grid Access Provider
Request is successfully sent from the Ediel portal to Elhub

5. Receive NotifyMeteringPointCharacteristics to DDQ

  • Document type: E58
NotifyMeteringPointCharacteristics is received to DDQ