SYS-DDQ301-01 Update master data - balance supplier
| Test ID | SYS-DDQ301-01 | 
| BRS's | BRS-NO-103 BRS-NO-301 | 
| Roles | DDQ | 
| Preconditions | Metering point should have metering point status E22 (active) in Elhub | 
| Postconditions | |
| Optional/Mandatory | Mandatory | 
| Test steps | Expected Result | 
| 1. Send BRS-NO-103 to Elhub 
 | Request is successfully sent | 
| 2. Receive ConfirmStartOfSupply to DDQ (optional) 
 | ConfirmStartOfSupply is received to DDQ | 
| 3. Receive NotifyStartOfSupply to DDQ after cancellation deadline 
 | NotifyStartOfSupply is received to DDQ | 
| 4. Send BRS-NO-301 to Elhub 
 | Request is successfully sent | 
| 5. Receive Acknowledgement to DDQ (optional) 
 | Positive Acknowledgement is received to DDQ | 