SYS-DDQ214-01 Receive deactivation of metering point from grid owner
Test ID | SYS-DDQ214-01 |
BRS's | BRS-NO-103 BRS-NO-214 |
Roles | DDM DDQ |
Preconditions | Metering point should have metering point status E22 (active) in Elhub |
Postconditions | |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
1. Send BRS-NO-103 to Elhub
| Request is successfully sent |
2. Receive ConfirmStartOfSupply to DDQ (optional)
| ConfirmStartOfSupply is received to DDQ |
3. Receive NotifyStartOfSupply to DDQ
| NotifyStartOfSupply is received to DDQ |
4. DDM sends BRS-NO-214 to Elhub
| Request is successfully sent from the Ediel portal to Elhub |
5. Receive NotifyEndOfSupply to DDQ
| NotifyEndOfSupply is received to DDQ |