SYS-DDQ102-05-B
This testcase requires that your system supports both balance supplier and grid owner roles
If you system only supports balance supplier roles you can run SYS-DDQ102-05-B instead
Test ID | SYS-DDQ102-05-B |
Description | Send a move in on an inactive metering point with StartOfSupply on todays date - From balance supplier Activate the metering point on todays date - From grid owner |
BRS's | BRS-NO-102, BRS-NO-122 |
Roles | DDQ, DDM |
Preconditions | Metering point should be consumption, non profiled and have metering point status 'Inactive' in Elhub |
Postconditions | The metering point status is 'Active' in Elhub and a new balance supply contract is created for the metering point in both DDQ's and DDM's system with the correct move in date |
Optional/Mandatory | Optional |
Test steps | Expected Result |
| Request is successfully sent |
2. Receive ConfirmStartOfSupply to DDQ (optional)
| ConfirmStartOfSupply is received to DDQ |
3. Receive NotifyStartOfSupply to DDM | NotifyStartOfSupply is received to DDM |
4. DDM sends BRS-NO-122 with StartOfOccurrence on todays date to activate metering point | Request is successfully sent |
5. Receive NotifyStartOfSupply to DDM | NotifyStartOfSupply is received to DDM |
6. Receive NotifyStartOfSupply to DDQ | NotifyStartOfSupply is received to DDQ |
7. Verify that both DDQ's and DDM's system is updated correctly | Metering point is active in Elhub and a new balance supply contract is created from correct move in date |