SYS-DDQ102-03 Rejection of start of supply - move in - in the future
Test ID | SYS-DDQ102-03 |
BRS's | BRS-NO-102 |
Roles | DDQ |
Preconditions | The change date must be in the future The metering point does not exist |
Postconditions | The start of supply is rejected The old balance supply contract has not been updated |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
1. Send BRS-NO-102 to Elhub
| Request is successfully sent |
2. Receive RejectStartOfSupply to DDQ
| RejectStartOfSupply is received to DDQ |