SYS-DDQ102-02 Cancellation of start of supply - move in - in the future
Test ID | SYS-DDQ102-02 |
BRS's | BRS-NO-102 |
Roles | DDQ |
Preconditions | The change date must be in the future Metering point should have metering point status E22 (active) in Elhub |
Postconditions | The start of supply is cancelled The old balance supply contract has not been updated |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
1. Send BRS-NO-102 to Elhub
| Request is successfully sent |
2. Receive ConfirmStartOfSupply to DDQ (optional)
| ConfirmStartOfSupply is received to DDQ |
3. Send BRS-NO-102 to Elhub
| Request is successfully sent |
4. Receive ConfirmStartOfSupply to DDQ (optional)
| ConfirmStartOfSupply is received to DDQ |