SYS-DDQ102-02 Cancellation of start of supply - move in - in the future
| Test ID | SYS-DDQ102-02 |
| BRS's | BRS-NO-102 |
| Roles | DDQ |
| Preconditions | The change date must be in the future Metering point should have metering point status E22 (active) in Elhub |
| Postconditions | The start of supply is cancelled The old balance supply contract has not been updated |
| Optional/Mandatory | Mandatory |
| Test steps | Expected Result |
1. Send BRS-NO-102 to Elhub
| Request is successfully sent |
2. Receive ConfirmStartOfSupply to DDQ (optional)
| ConfirmStartOfSupply is received to DDQ |
3. Send BRS-NO-102 to Elhub
| Request is successfully sent |
4. Receive ConfirmStartOfSupply to DDQ (optional)
| ConfirmStartOfSupply is received to DDQ |