SYS-DDM601-01 Response from Grid Access Provider
| Test ID | SYS-DDM601-01 | 
| Description | Response from Grid Access Provider | 
| BRS's | BRS-NO-601 | 
| Roles | DDQ, DDM | 
| Preconditions | Metering point should have metering point status E22 (active) in Elhub 
 | 
| Postconditions | Positive acknowledgement have been received | 
| Optional/Mandatory | Mandatory | 
| Test steps | Expected Result | 
| 1. DDQ sends BRS-NO-601 to Elhub 
 | Request is successfully sent from the Ediel portal to Elhub | 
| 2. Receive RequestToGridAccessProvider to DDM 
 | RequestToGridAccessProvider is received to DDM | 
| 3. Send BRS-NO-601 to Elhub 
 | Response is successfully sent | 
| 4. Receive Acknowledgement to DDM (optional?) 
 | Acknowledgement is received to DDM | 