Test IDSYS-DDM223-01
DescriptionRollback of deactivation of metering point
BRS's

BRS-NO-212

BRS-NO-223

RolesDDM
Preconditions

Metering point should have metering point status E22 (active) in Elhub

Postconditions

Metering point status is still active

Optional/MandatoryMandatory
Test stepsExpected Result
  1. Send BRS-NO-212 to Elhub
  • Message: RequestUpdateMasterDataMeteringPoint
  • Document type: E58
Request is successfully sent

2. Receive Acknowledgement to DDM (optional)

  • Document type: 294
Acknowledgement is received to DDM

3. Send BRS-NO-223

  • Message: RequestUpdateMasterDataMeteringPoint
  • Document type: E67

RequestUpdateMasterDataMeteringPoint is received to Elhub

4. Receive Acknowledgement to DDM (optional)

  • Document type: 294
Acknowledgementis received to DDM
5. Verify that DDM's system is updated correctlyThe BRS-NO-212 is rolled back and the metering point status is still active