SYS-DDM222-01 Rollback of move out from metering point - from grid owner
Test ID | SYS-DDM222-01 |
Description | Rollback of move out from metering point - from grid owner |
BRS's | BRS-NO-211 BRS-NO-222 |
Roles | DDM |
Preconditions | Metering point should have metering point status E22 (active) in Elhub Metering point should have an active balance supply contract |
Postconditions | The balance supply contract have been reopened |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
| Request is successfully sent |
2. Receive ConfirmEndOfSupply to DDM (optional)
| ConfirmEndOfSupply is received to DDM |
3. Send BRS-NO-222
| RequestEndOfSupply is received to Elhub |
4. Receive ConfirmEndOfSupply to DDM (optional)
| ConfirmEndOfSupply is received to DDM |
5. Receive NotifyStartOfSupply to DDM
| NotifyStartOfSupply is received to DDM |
6. Verify that DDM's system is updated correctly | The BRS-NO-211 is rolled back and the balance supply contract have been reopened |