SYS-DDM214-01 Deactivation of metering point with an active balance supply contract Test IDSYS-DDM214-01DescriptionDeactivation of metering point with an active balance supply contractBRS'sBRS-NO-214RolesDDQ/ DDMPreconditionsMetering point should have metering point status E22 (active) in ElhubMetering point should have active contract with Grid Access ProviderMetering point should have active contract with Balance SupplierPostconditionsMetering point should have metering point status E23 (inactive) in ElhubOptional/MandatoryMandatoryTest stepsExpected ResultSend BRS-NO-214 to ElhubMessage: RequestUpdateMasterDataMeteringPointDocument type: E58Request is successfully sent2. Receive Acknowledgement to DDM (optional)Document type: 294Acknowledgement is received to DDM3. Verify that DDM's system is updated correctlyMetering point should be marked as inactive and the Grid Access contract on the metering point is ended on the change date ×