SYS-DDM214-01 Deactivation of metering point with an active balance supply contract

Test IDSYS-DDM214-01
DescriptionDeactivation of metering point with an active balance supply contract
BRS's

BRS-NO-214

RolesDDQ/ DDM
Preconditions

Metering point should have metering point status E22 (active) in Elhub

Metering point should have active contract with Grid Access Provider

Metering point should have active contract with Balance Supplier

Postconditions

Metering point should have metering point status E23 (inactive) in Elhub

Optional/MandatoryMandatory
Test stepsExpected Result
  1. Send BRS-NO-214 to Elhub
  • Message: RequestUpdateMasterDataMeteringPoint
  • Document type: E58
Request is successfully sent

2. Receive Acknowledgement to DDM (optional)

  • Document type: 294
Acknowledgement is received to DDM
3. Verify that DDM's system is updated correctlyMetering point should be marked as inactive and the Grid Access contract on the metering point is ended on the change date