SYS-DDM214-01 Deactivation of metering point with an active balance supply contract
| Test ID | SYS-DDM214-01 |
| Description | Deactivation of metering point with an active balance supply contract |
| BRS's | BRS-NO-214 |
| Roles | DDQ/ DDM |
| Preconditions | Metering point should have metering point status E22 (active) in Elhub Metering point should have active contract with Grid Access Provider Metering point should have active contract with Balance Supplier |
| Postconditions | Metering point should have metering point status E23 (inactive) in Elhub |
| Optional/Mandatory | Mandatory |
| Test steps | Expected Result |
| Request is successfully sent |
2. Receive Acknowledgement to DDM (optional)
| Acknowledgement is received to DDM |
| 3. Verify that DDM's system is updated correctly | Metering point should be marked as inactive and the Grid Access contract on the metering point is ended on the change date |