SYS-DDM211-02 Cancellation of move out from Grid Access Provider
Test ID | SYS-DDM211-02 |
Description | Cancellation of move out from Grid Access Provider |
BRS's | BRS-NO-211 |
Roles | DDM |
Preconditions | Metering point should have metering point status E22 (active) in Elhub Metering point should have active contract with Grid Access Provider |
Postconditions | The Grid Access contract on the metering point has not been changed |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
| Request is successfully sent |
2. Receive ConfirmEndOfSupply to DDM (optional)
| ConfirmEndOfSupply is received to DDM |
3. Send BRS-NO-211 to Elhub
| Request is successfully sent |
4. Receive ConfirmEndOfSupply to DDM (optional)
| ConfirmEndOfSupply is received to DDM |
5. Verify that DDM's system is updated correctly | The BRS-NO-211 is cancelled and the Grid Access contract on the metering point has not been changed |