SYS-DDM102-04-B
This testcase requires that your system supports both grid owner and balance supplier roles
If you system only supports grid owner roles you can run SYS-DDM102-05-A instead
Test ID | SYS-DDM102-04-B |
Description | Send a move in on an inactive metering point with StartOfSupply on todays date |
BRS's | BRS-NO-102 |
Roles | DDQ, DDM |
Preconditions | Metering point should be consumption, non profiled and have metering point status 'Inactive' in Elhub |
Postconditions | The metering point status is still 'Inactive' in Elhub and no new contract is created for the metering point in DDM's or DDQ's system |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
| Request i successfully sent |
2. DDQ receives ConfirmStartOfSupply (optional)
| ConfirmStartOfSupply is received to DDQ |
3. DDM receives NotifyStartOfSupply from Elhub | NotifyStartOfSupply is received to DDM |
4. DDM sends RejectStartOfSupply with error code "EH095 - Metering point cannot be activated" to Elhub | RejectStartOfSupply is successfully sent |
5. DDQ receives RejectStartOfSupply with error code "EH095 - Metering point cannot be activated" from Elhub | RejectStartOfSupply is received to DDQ |
6. Verify that both DDQ's and DDM's system is updated correctly | Metering point is still inactive in Elhub and no new contract is created on the metering point in DDM's or DDQ's system |