SYS-DDM102-04-B

This testcase requires that your system supports both grid owner and balance supplier roles
If you system only supports grid owner roles you can run SYS-DDM102-05-A instead

Test IDSYS-DDM102-04-B
DescriptionSend a move in on an inactive metering point with StartOfSupply on todays date
BRS's

BRS-NO-102

RolesDDQ, DDM
Preconditions

Metering point should be consumption, non profiled and have metering point status 'Inactive' in Elhub

Postconditions

The metering point status is still 'Inactive' in Elhub and no new contract is created for the metering point in DDM's or DDQ's system

Optional/MandatoryMandatory
Test stepsExpected Result
  1. DDQ sends BRS-NO-102 to Elhub with StartOfSupply on todays date
  • Message: RequestStartOfSupply
  • Document type: 392
Request i successfully sent

2. DDQ receives ConfirmStartOfSupply (optional)

  • Document type: 414
ConfirmStartOfSupply is received to DDQ
3. DDM receives NotifyStartOfSupply from ElhubNotifyStartOfSupply is received to DDM
4. DDM sends RejectStartOfSupply with error code "EH095 - Metering point cannot be activated" to ElhubRejectStartOfSupply is successfully sent
5. DDQ receives RejectStartOfSupply with error code "EH095 - Metering point cannot be activated" from ElhubRejectStartOfSupply is received to DDQ
6. Verify that both DDQ's and DDM's system is updated correctlyMetering point is still inactive in Elhub and no new contract is created on the metering point in DDM's or DDQ's system