SYS-DDM102-01 Receive information about Move in
sult
Test ID | SYS-DDM102-01 |
Description | Receive information about Move in - from Balance supplier |
BRS's | BRS-NO-102 |
Roles | DDQ, DDM |
Preconditions | Metering point should have metering point status E23 (inactive) in Elhub |
Postconditions | A new balance supply contract is created for the metering point in DDM's system |
Optional/Mandatory | Mandatory |
Test steps | Expected Result |
| Message is successfully sent |
2. Receive positive acknowledgement to DDM (optional)
| Positive Acknowledgement is received to DDM |
3. DDQ sends BRS-NO-102 to Elhub
| Request is successfully sent from the Ediel portal to Elhub |
4. Receive NotifyStartOfSupply to DDM
| NotifyStartOfSupply is received by DDM |
5. Verify that DDM's system is updated correctly | A new balance supply contract is created for the metering point |