SYS-DDQ101-02 Cancellation of change of supplier
| Test ID | SYS-DDQ101-02 | 
| BRS's | BRS-NO-101  | 
| Roles | DDQ | 
| Preconditions | Metering point should have metering point status E22 (active) in Elhub The metering point must have an active end user  | 
| Postconditions | The change of supplier is cancelled The old balance supply contract has not been updated  | 
| Optional/Mandatory | Mandatory | 
| Test steps | Expected Result | 
1. Send BRS-NO-101 to Elhub 
  | Request is successfully sent | 
2. Receive ConfirmStartOfSupply to DDQ (optional) 
  | ConfirmStartOfSupply is received to DDQ | 
3. Send BRS-NO-101 to Elhub 
  | Request is successfully sent | 
4. Receive ConfirmStartOfSupply to DDQ (optional) 
  | ConfirmStartOfSupply is received to DDQ |