SYS-DDM101-01 Receive information from Change of supplier
| Test ID | SYS-DDM101-01 | 
| Description | Receive information from Change of Supplier from Balance supplier | 
| BRS's | BRS-NO-101 | 
| Roles | DDM, DDQ | 
| Preconditions | Metering point must have status active (E22) in Elhub | 
| Postconditions | Balance supplier is changed on metering point in DDM's system | 
| Optional/Mandatory | Mandatory | 
| Test steps | Expected Result | 
| 
 
 | Request is successfully sent from the Ediel portal to Elhub | 
| 2. Elhub confirms Move in | Step 2 is approved | 
| 3. DDQ sends BRS-NO-101 to Elhub 
 | Request is successfully sent from the Ediel portal to Elhub | 
| 4. Elhub confirms Change of Supplier | Step 5 is approved | 
| 5. Receive NotifyStartOfSupply to DDM 
 | NotifyStartOfSupply is received by DDM | 
| 6. Verify that DDM's system is updated correctly | Balance Supplier is changed on metering point | 