08 - Aftermath
Sist oppdatert 2019-02-25 10:50Edielportalen:
Go Live 08 <Rolle> Aftermath
Execution period
Elhub Go Live: The activities in this section are executed in the period 25/2 to 1/5.
Summary of activities
This chapter includes activities for verifying parameters in EIP before reconciliation, database backup of DAM and decomissioning of the same.
Content overview
- 8.1 Process and verifications
- 8.2 Decomissioning of DAM
Commissioning steps
Task ID | Commissioning step | Start time | Deadline | Execution Organization | Step description | Done |
8.1 Process and verifications | ||||||
8.1.0 | Split HBase table (should be done 1 day to 3 months after market parties starts sending MV's, see prerequisite) | To be done in the regular change process | N/A | Accenture | Split HBase table Prerequisite: There must be at least one meter value for at least 95% of all metering points in the HBase table. | |
8.1.1 | Tredjeparter kan spørre om historiske måleverdier | 25/2 | Tredjeparter | Fra og med dette tidspunktet kan tredjeparter spørre om historiske måleverdier. | NA | |
8.1.2 | Verify parameters recon.maxDaysSinceUsgDtForGAStatusVerTimeChk and recon.maxReconAllowedSpanDays ElhubGoLiveDate | 25/2 | Statnett | Report value of parameters to Calculation responsible from Statnett. | ||
8.1.3 | Kvalitetssikre betalingsinformasjon fra IFS for aktører i Elhub | 25/2-14/3 | Statnett | Kvalitetssikre betalingsdetaljer for aktører for å sikre at første fakturering sendes ut og til riktig mottaker (Under Fakturadetaljer: IFS-kundenummer, e-postadresse, postnummer, poststed. Kan SQL spørring / OBIEE rapport lages som sammenligningsgrunnlag) | ||
8.2 Decomissioning of DAM | ||||||
8.2.1 | EDM Database logical backup | 25/2 | Accenture | Take the final logical backup of EDM database before decommissioning. https://confluence.elhub.org/display/IS/CRB+BACKUP+USING+LOGICAL+BACKUP+METHOD | ||
8.2.2 | Decommissioning of DAM and rsync | 1/5 09:00 To be done in the regular change process | 1/5 17:00 | Accenture | Remove servers and discontinue SLA for DAM Remove endpoints on BigIP
| |
8.2.3 | Clean up EnergyIP servers for DAM | 1/5 09:00 To be done in the regular change process | 1/5 17:00 | Accenture | Remove migration folders on EnergyIP servers, delete applications only used in migration, ... |