08 - Aftermath

Sist oppdatert 2019-02-25 10:50

Edielportalen:

  • Go Live 08 <Rolle> Aftermath

Execution period

Elhub Go Live: The activities in this section are executed in the period 25/2 to 1/5.

Summary of activities

This chapter includes activities for verifying parameters in EIP before reconciliation, database backup of DAM and decomissioning of the same.


Content overview

  • 8.1 Process and verifications
  • 8.2 Decomissioning of DAM



Commissioning steps


Task ID Commissioning step Start time Deadline Execution Organization Step description

Done

8.1 Process and verifications
8.1.0

Split HBase table

(should be done 1 day to 3 months after market parties starts sending MV's, see prerequisite)

To be done in the regular change process

N/A

Accenture

Split HBase table

Prerequisite: There must be at least one meter value for at least 95% of all metering points in the HBase table.

Split HBase Table

  •  


8.1.1

Tredjeparter kan spørre om historiske måleverdier

25/2



Tredjeparter

Fra og med dette tidspunktet kan tredjeparter spørre om historiske måleverdier.


NA
8.1.2

Verify parameters recon.maxDaysSinceUsgDtForGAStatusVerTimeChk and recon.maxReconAllowedSpanDays

ElhubGoLiveDate


25/2
Statnett

See: How to Verify parameters recon.maxDaysSinceUsgDtForGAStatusVerTimeChk and recon.maxReconAllowedSpanDays

Report value of parameters to Calculation responsible from Statnett.

  •  
8.1.3 Kvalitetssikre betalingsinformasjon fra IFS for aktører i Elhub 25/2-14/3
Statnett

Kvalitetssikre betalingsdetaljer for aktører for å sikre at første fakturering sendes ut og til riktig mottaker

(Under Fakturadetaljer: IFS-kundenummer, e-postadresse, postnummer, poststed. Kan SQL spørring / OBIEE rapport lages som sammenligningsgrunnlag)

  •  


8.2 Decomissioning of DAM
8.2.1 EDM Database logical backup 25/2
Accenture

Take the final logical backup of EDM database before decommissioning.

https://confluence.elhub.org/display/IS/CRB+BACKUP+USING+LOGICAL+BACKUP+METHOD


  •  


8.2.2 Decommissioning of DAM and rsync

1/5

09:00

To be done in the regular change process

1/5

17:00

Accenture

Remove servers and discontinue SLA for DAM

Decommissioning of DAM

Remove endpoints on BigIP

(warning) Decomission rsync servers, SFTP in OAG and endpoints in BIG-IP LTM.

  •  


8.2.3 Clean up EnergyIP servers for DAM

1/5

09:00

To be done in the regular change process

1/5

17:00

Accenture

Remove migration folders on EnergyIP servers, delete applications only used in migration, ...

EDM Decommissioning Components from Energy IP

  •