22 - End in metering point - from Grid Access Provider
End in metering point – from Grid Access Provider
This process is generally used for deactivation of a metering point due to customer move out in case the customer is informing the grid access provider directly of the move out instead of the balance supplier.
The following business processes are supported:
- Customer move out
- Cancellation/rollback of customer move out
The process starts with the message Request end of supply from the grid access provider to Elhub. If the validation of the message is OK and the element regarding positive acknowledgement is set in the Header class, the message ConfirmEndOfSupply is returned. If the message violates the validation rules the message RejectEndOfSupply is returned.
Sequence diagram end in metering point – from grid access provider
Messages end in metering point – from grid access provider
The messages used in the process are described below.
Request End of Supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 432 | UN/CEFACT | Notification of contract termination |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-211 | Elhub | Move out from metering point - from grid owner |
BRS-NO-222 | Elhub | Rollback of move out | |
Business Process Role | DDM | UN/CEFACT | Grid access provider |
Message Implementation Guide
Ref. RequestEndOfSupply
Confirm end of supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 406 | UN/CEFACT | Notification to supplier of contract termination |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-211 | Elhub | Move out from metering point - from grid owner |
BRS-NO-222 | Elhub | Rollback of move out | |
Business Process Role | DDM | UN/CEFACT | Grid access provider |
Message Implementation Guide
Ref. ConfirmEndOfSupply
Reject end of supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 406 | UN/CEFACT | Notification to supplier of contract termination |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-211 | Elhub | Move out from metering point - from grid owner |
BRS-NO-222 | Elhub | Rollback of move out | |
Business Process Role | DDM | UN/CEFACT | Grid access provider |
ResponseReason | E10 | ebIX | Metering point not identifiable |
E16 | ebIX | Unauthorized balance supplier | |
E17 | ebIX | Requested switch date not within time limits | |
E22 | ebIX | Metering point blocked for switching |
Message Implementation Guide
Ref. RejectEndOfSupply