13 - Start in metering point - from Grid Access Provider
Start in metering point – from Grid Access Provider
This process is generally used for activation of a metering point due to a customer move in.
The following business processes are supported:
- Customer move in
- Cancellation/rollback of customer move in
The process starts with the message Request start of supply from the grid access provider to Elhub. If the validation of the message is OK and the element regarding positive acknowledgement is set in the Header class, the message ConfirmStartOfSupply is returned. If the message violates the validation rules the message RejectStartOfSupply is returned.
If a meter read is needed, the message CollectedData must be sent to Elhub.
Sequence diagram start in metering point – from grid access provider
Messages start in metering point – from grid access provider
The messages used in the process are described below.
Request start of supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 392 | UN/CEFACT | Request change of supplier |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-123 | Elhub | New grid access contract - move in |
BRS-NO-133 | Elhub | Rollback of new grid access contract | |
Business Process Role | DDM | UN/CEFACT | Grid access provider |
Message Implementation Guide
Ref. RequestStartOfSupply
Confirm start of supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 414 | UN/CEFACT | Acknowledgement of change of supplie |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-123 | Elhub | New grid access contract - move in |
BRS-NO-133 | Elhub | Rollback of new grid access contract | |
Business Process Role | DDM | UN/CEFACT | Grid access provider |
Message implementation guide
Ref. ConfirmStartOfSupply
Reject start of supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 414 | UN/CEFACT | Acknowledgement of change of supplie |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-123 | Elhub | New grid access contract - move in |
BRS-NO-133 | Elhub | Rollback of new grid access contract | |
Business Process Role | DDM | UN/CEFACT | Grid access provider |
ResponseReason | E10 | ebIX | Metering point not identifiable |
E16 | ebIX | Unauthorized balance supplier | |
E17 | ebIX | Requested switch date not within time limits | |
E22 | ebIX | Metering point blocked for switching | |
.. | .. |
Message Implementation Guide
Ref. RejectStartOfSupply