Code | Description |
---|
BRS-NO-101 | Start of supply - change of supplier |
BRS-NO-102 | Start of supply - move in - in the future |
BRS-NO-103 | Start of supply - move in - back in time |
BRS-NO-104 | Change of supplier from last resort |
BRS-NO-111 | Rollback - start of supply |
BRS-NO-121 | New metering point |
BRS-NO-122 | Activation of metering point |
BRS-NO-123 | New grid access contract - move in |
BRS-NO-131 | Rollback of new metering point |
BRS-NO-132 | Rollback of activation of metering point |
BRS-NO-133 | Rollback of new grid access contract |
BRS-NO-201 | End of supply due to move out |
BRS-NO-202 | End of supply |
BRS-NO-211 | Move out from metering point - from grid access provider |
BRS-NO-212 | Deactivation of metering point |
BRS-NO-213 | Removal of metering point |
BRS-NO-214 | Deactivation of metering point with end user |
BRS-NO-221 | Rollback of end of supply |
BRS-NO-222 | Rollback of move out |
BRS-NO-223 | Rollback of deactivation of metering point |
BRS-NO-224 | Rollback of removal of metering point |
BRS-NO-301 | Update master data - balance supplier |
BRS-NO-302 | Update master data - grid owner |
BRS-NO-303 | Request master data |
BRS-NO-305 | Changes initiated by Elhub |
BRS-NO-306 | Settlement type change |
BRS-NO-311 | Metering reading and expected annual consumption from balance supplier |
BRS-NO-312 | Reporting of metering values for profiled metering points |
BRS-NO-313 | Reporting of metering values for non-profiled metering points |
BRS-NO-314 | Reminders of metering values to metered data responsible |
BRS-NO-315 | Request for metering values |
BRS-NO-317 | Update expected annual consumption |
BRS-NO-318 | Update grid loss parameters |
BRS-NO-321 | Quality assurance - grid owner |
BRS-NO-322 | Preliminary profiles consumption to to balance supplier |
BRS-NO-324 | Request basis for settlement - balance supplier/responsible |
BRS-NO-332 | Withdrawal of metering values for profiled metering points |
BRS-NO-402 | Corrections of master data - from grid owner |
BRS-NO-501 | Report structure data for imbalance settlement |
BRS-NO-502 | Reporting data for imbalance settlement |
BRS-NO-503 | Reporting data for reconciliation |
BRS-NO-511 | Reporting produced volume to registry responsible elcertificates |
BRS-NO-512 | Reporting quota obliged consumption elcertificates |
BRS-NO-601 | Request to grid owner |
BRS-NO-611 | Pre-switch check og metering point characteristics |
BRS-NO-622 | Update 3rd party access |
BRS-NO-623 | Overview of 3rd party access |
POLL | Polling of messages |