11 - End of supply - to Balance Supplier
End of supply – to Balance Supplier
This process is generally used to terminate a supply contract in a metering point due to change of balance supplier or customer move out. In case of change of balance supplier this process is used to inform the previous balance supplier of the termination of the contract.
Sequence diagram end of supply – to balance supplier
Message end of supply – to balance supplier
The only message used in this process is described below.
Notify End of supply
Code usage
Element name | Code | Code list | Description |
---|---|---|---|
Document Type | 406 | UN/CEFACT | Notification to supplier of contract termination |
E02 | ebIX | Cancellation of supply | |
Business Process | BRS-NO-101 | Elhub | Start of supply - Change of supplier |
BRS-NO-102 | Elhub | Start of supply - move in - in the future | |
BRS-NO-103 | Elhub | Start of supply - move in - back in time | |
BRS-NO-104 | Elhub | Change of supplier from last resort | |
BRS-NO-111 | Elhub | Rollback - start of supply | |
BRS-NO-123 | Elhub | New grid access contract - move in | |
BRS-NO-133 | Elhub | Rollback of new grid access contract | |
BRS-NO-211 | Elhub | End of supply due to move out | |
BRS-NO-214 | Elhub | Deactivation of metering point with end user | |
BRS-NO-222 | Elhub | Rollback of move out | |
BRS-NO-305 | Elhub | Changes to meteringpoint initiated by Elhub | |
Business Process Role | DDQ SLR | UN/CEFACT Elhub | Balance Supplier Balance Supplier of Last Resort |
Message Implementation Guide
Ref. NotifyEndOfSupply